• Ingen resultater fundet

Framework for Railway Phase-based Planning

N/A
N/A
Info
Hent
Protected

Academic year: 2022

Del "Framework for Railway Phase-based Planning"

Copied!
20
0
0

Indlæser.... (se fuldtekst nu)

Hele teksten

(1)

Framework for Railway Phase-based Planning

Rui Li, ruli@transport.dtu.dk DTU Transport

August 27th, 2013

(2)

27/08/2013 2 DTU Transport, Technical University of Denmark

Agenda

• Introduction

o Track Behavior

• Life Cycle Cost

• Phase-based Planning Framework

• Policy Discussion and Case Study

• Conclusions

(3)

27/08/2013 3 DTU Transport, Technical University of Denmark

Introduction - Background

•Performance

o Better Punctuality o More trains per hours o Longer operation hours

•Reliability

•Budget pressures

•Operational restrictions

How to improve the cost efficiency of railway infrastructure projects?

(4)

27/08/2013 4 DTU Transport, Technical University of Denmark

Introduction - Track Behavior

𝑄 = 𝑄0 ∗ e−b∗t - Q0 denotes the initial track quality

- b is the rate of deterioration over time t.

(5)

27/08/2013 5 DTU Transport, Technical University of Denmark

Life Cycle Costs approach

Reducing maintenance cost without reducing maintenance itself !

(6)

27/08/2013 6 DTU Transport, Technical University of Denmark

Why Life Cycle Costs – An Example

Interest Rate 0%

Gross Maintenance cost 1.500 DKK/meter Initial Investment 4.500 DKK/meter

Maintenance every 8 years Sum 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Track Installation 1,0 1

Maintenance 11,0 1 1 1 1 1 1 1 1 1 1 1

Annuity 609

Maintenance every 5 years Sum 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Track Installation 1,0 1

Maintenance 7,0 1 1 1 1 1 1 1

NPV 15.000

Annuity 469

130%

Achievements from the both sides?

Higher quality Track

Cheaper LCC (10%)

(7)

27/08/2013 7 DTU Transport, Technical University of Denmark

The Limitation of the Existing LCC Approach

• Planned Costs

• Unplanned Costs – Repairs

– Track availibility

• Passenger Loss

• Train Operators Costs – Train-Buses

– Announcements – Rolling Stock

Maintenance

• Riding Comforts – Vibration – Noise – Accidents

• Pollutions

LCC %

Direct Costs 130%

+ Train penality 166%

+ Interates rate 3% 132%

+ Passenger Loss 142%

+ Working possessions + Train operators + Environment Impacts

... ...

(8)

27/08/2013 8 DTU Transport, Technical University of Denmark

Life Cycle Cost Scope

• A Larger LCC Scope

• Different Cost Types

• Planning is complex and time comsuming

 A planning framework is needed!

(9)

27/08/2013 9 DTU Transport, Technical University of Denmark

A Phase-based Planning Framework

Why phase-based?

• Input General Profiles

• Estimating Traffic

• Planning Maintenance and Renewals

• Possession Time Estimating

• Estimating the Failure Penalty

• Estimating the costs for Train Operators and Passengers

• Output the Overview of the Life Cycle Cost Annuity

(10)

27/08/2013 10 DTU Transport, Technical University of Denmark

Framework Outputs

(11)

27/08/2013 11 DTU Transport, Technical University of Denmark

Case Study - Policy Discussion 1

High Quality Track

- High Construction Cost - Maintenance every 5 years

Low Quality Track

- Low Construction Costs - Maintain it every 3 years

VS.

(12)

27/08/2013 12 DTU Transport, Technical University of Denmark

High Quality Track vs. Low Quality Track

Initial Quality Low High

Initial Investment (DKK/T-meter) 3.500 4.500 Track Installation 1 1 Maintenance 6 7 Life Time 21 32

Maintenance every 3 years 5 years

(13)

27/08/2013 13 DTU Transport, Technical University of Denmark

High Quality Track vs. Low Quality Track

(14)

27/08/2013 14 DTU Transport, Technical University of Denmark

Case Study - Policy Discussion 2

Positive renew

- Renew the track system when it reached threshold

Standard renew

- Maintenance the track when it reached threshold

VS.

(15)

27/08/2013 15 DTU Transport, Technical University of Denmark

Postive Renewal vs. Standard Renewal

Interest Rate 0%

Gross Maintenance cost 500DKK/meter Average delay minutes per train minutes5 Average Cancallation factor 15minutes DKK per delayed train-hour 5.000DKK DKK Per cancelled train-hour 100.000DKK Line Length 5.000meter

Double Track yes

Initial Investment 6.000DKK/meter 50,0 100,0 150,0 200,0 250,0 300,0 350,0 400,0 450,0

A: Life Time 25 years B: Life Time 28 years C: Life Time 32 years D: Life Time 35 years

Life Span (years) 25 28 32 35

Maintenance Amount 4 5 7 10

(16)

27/08/2013 16 DTU Transport, Technical University of Denmark

Case Study

Concrete Sleepers Timber Sleepers

• Long Service Life

• Less Maintenance

• Higher axle-load

• Cheap

• Less heavy

• Absorb forces

(17)

27/08/2013 17 DTU Transport, Technical University of Denmark

Case Study - Assumptions

Items Concrete Timber

Service Life (years) 35 25

Price (per track-meter) 4.500 4.000

Tamping every 5 years 3 years

Life Time (without maintenance) 12 9

-30,0 -25,0 -20,0 -15,0 -10,0 -5,0 -

0 5 10 15 20 25 30 35 40

Track Behavior and Life Time

Threhold Timber Concrete

(18)

27/08/2013 18 DTU Transport, Technical University of Denmark

Case Study - Life Cycle Cost Overview

(19)

27/08/2013 19 DTU Transport, Technical University of Denmark

Conclusions

• Life Cycle Cost Approach can improve cost efficient

• A larger scope of Life Cycle Cost gives a better cost picture

(20)

27/08/2013 20 DTU Transport, Technical University of Denmark

Questions?

Referencer

RELATEREDE DOKUMENTER

However, often the decision of introducing solar cells in the windows should be based on oth- er reasons than energy: cost (e.g. cost of pv windows, reduction of cooling plant),

Release office space resulting in a tangible benefit in support of GCF meeting their Group Cost Challenge. Provide the cost-savings over a short timescale (prior to move to

Hedvig Vestergaard, hev@sbi.aau.dk Danish Building Research Institute, SBi Aalborg University... How do residential areas recreate their

[10] , The Framework is mainly to plan the strategic (+5 years) track system maintenance and renewal work. The Life Cycle Cost estimation is defined into the following phases.. Phase

the state reward (or cumulative reward) gives the cost of staying in a given state measured per time unit. the transition reward (or instantaneous or impulse reward) gives

The operation phase of a building’s life cycle accounts for the largest share of the energy use. In the last decade, efforts have been made to reduce the energy needed for

A) Increasing the number of Hubs may not be a cost-effective choice for some time in order to amortize the cost for electro-optical conversion and for the Optical NoC

The COVID-19 crisis has shown us the importance of a life science industry and a world-class healthcare system – and the importance of them being able to interact We must