• Ingen resultater fundet

Socio-economic analyses in perspective: Uncertainties and bias in decision support

N/A
N/A
Info
Hent
Protected

Academic year: 2022

Del "Socio-economic analyses in perspective: Uncertainties and bias in decision support"

Copied!
24
0
0

Indlæser.... (se fuldtekst nu)

Hele teksten

(1)

Socio-economic analyses in perspective:

Uncertainties and bias in decision support

Associate Professor, PhD Kim Bang Salling

DTU Transport

Traffic days in Aalborg 2012 –

Special session: “Uncertainties in Transport Project Evaluation (UNITE)”

(2)

Project Plan of UNITE

Uncertainties in Transport Project Evaluation (UNITE): the five Work-Packages

(5) Evaluation methodology

WP5 project leader: Steen Leleur (DMG)

(4) Uncertainty calculation in transport models WP4 project leader: Otto Anker Nielsen (TMG)

(2) Organizational context of Modelling, an empirical study

WP2 project leader: Petter Næss (AAU) (3) Uncertainty calculation of cost

estimates

WP3 project leader: Bo Friis Nielsen (DTU Informatics)

(1) Systematic biases in transport models (recognized ignorance), an empirical study WP1 project leader: Petter Næss (AAU)

(3)

How do we evaluate transport projects?

• Various existing guideline report:

–Denmark, Sweden, UK, European Union, ....

• Socio-economic analysis by the use of Cost-Benefit Analysis (CBA)

• Produces single point estimates such as Net Present Values (NPV), Benefit Cost Ratios (BCR), etc

• However, no common rule have been set in order to acommodate the uncertainties in CBA!

–Recent conducted PhD dissertation proved this point

(4)

Background & Motivation

• The Manual for socio-economic analysis in the transport sector (2003)

–Unique guidelines for evaluating transport infrastructure projects

–Lack of uncertainty handling –Expected revision 2012-2013

(5)

How do we evaluate transport projects?

• However, no common rule have been set in order to acommodate the uncertainties in CBA!

–Recent conducted PhD dissertation proved this point

(6)

The Case Study: HH-Connection

• Connecting Denmark with Sweden: Scandinavian link –Currently, close to the capacity limit on Oresund

HH-Connection (alternatives*)

Description

(Alignment of connection)

Cost

(million DKK) Alternative 1 Tunnel for rail (2 tracks) person traffic only 7,700 Alternative 2 Tunnel for rail (1 track) goods traffic only 5,500 Alternative 3 Bridge for road and rail (2x2 lanes & 2 tracks) 11,500

Alternative 4 Bridge for road (2x2 lanes) 6,000

* Larsen, L.A. & Skougaard, B.Z. (2010). Vurdering af alternativer for en fast forbindelse Helsingør- Helsingborg, M.Sc. thesis, Department of Transport, Technical University of Denmark (in Danish)

(7)

The UNITE-DSS Modelling Framework

Todays Outline

(8)

Results: Cost-Benefit Analysis

• Construction costs – by far the largest contributor of costs

• User Benefits – by far the largest contributor of benefits – Consists of Ticket revenue and time savings

– Relies on the prognosis of future number of passengers i.e.

demand forecasts

HH-Connection (alternatives)

Cost

(million DKK)

BCR NPV

(million DKK)

Alternative 1 7,700 1.50 5,530

Alternative 2 5,500 0.16 -6,640

Alternative 3 11,500 2.71 28,240

Alternative 4 6,000 3.08 17,860

(9)

Are we telling the truth?!?!

Construction cost overruns

0%

200%

400%

600%

800%

1000%

1200%

1400%

1600%

1800%

2000%

Suez Canal Sydney Opera House Concorde Supersonic Aeroplane Boston's Artery/Tunnel Project, USA Humber Bridge, UK Boston- Washington- New York Great Belt Rail Tunnel, DK A6 Motorway Chapel-en-le- Frith/Whaley Shinkansen Joetsu Rail line, Japan Washington metro, USA Channel Tunnel, UK & France Karlsruhe- Bretten light rail, Germany Øresund Access links, DK & Sweden Mexico city metro line, Mexico Paris-Auber- Nanterre rail line, France

Cost Overruns (%)

Q: Have we learned anything from history?

”Chunnel” in 1987 £2,600 million (’85 prices) Completion 1994 £4,650 million (’85 prices) Total cost overrun of approx. 80%

”Øresund access link” in 1991 3.2 billion DKK (’90 prices) Completion 1998 5.4 billion DKK (’90 prices)

Total cost overrun of approx. 68%

(10)

Theoretical anchoring

The Transport Planning Phase: Adapted from the British Department for Transport (DfT) (2004)

Reference Class Forecasting: Optimism Bias

Inside View Outside View

”Uniqueness” of Project

”The Planning Fallacy”

Reference Class Forecasting

Forecasting of particular projects

Forecasting from a group of projects

(1) Identification of relevant reference

classes

(2) Establishing probability distribution

(3) Placing and comparing the

project

Optimism Bias Uplifts Current Situation

(11)

Optimism Bias and uplifts

• Deriving uplifts is highly dependet on large data-sets

–Flyvbjerg from (AAU) has since 2003 developed a large database

–Unfortunately, it looks upon mega-projects

• The basis is Reference Class Forecasting i.e. statistical measurements on various project pools

Source: Flyvbjerg and COWI (2004)

(12)

Results : Optimism Bias Uplifts

• The BCR are lower, however, still point estimates towards DM –Moreover an advanced form of sensitivity analysis

• Imply to introduce risk analysis and Monte Carlo simulation

HH-Connection (alternatives)

Cost (uplifted) (million DKK)

BCR (orig.) (from slide 8)

BCR (uplifts):

80% uplift

Alternative 1 12,090 1.50 0.97

Alternative 2 8,640 0.16 0.10

Alternative 3 15,180 2.71 1.75

Alternative 4 7,920 3.08 1.98

(13)

The UNITE Project Database (UPD)

• The convention used is as follows:

( ( ) )

forecasted forecasted actual

X X

U X − ×100

=

Over estimation of Demand

(14)

• Demand forecasts (user benefits) are derived:

– U is percent inaccuracy,

– Xa is the actual traffic after the project is opened – Xf is the forecasted traffic on the decision to build

• Combination of two database samples

0 5 10 15 20 25 30

(-120;-100) (-100;-80) (-80;-60) (-60;-40) (-40;-20) (-20;0) (0;20) (20;40) (40;60) (60;80) (80;100) (100;120) (120;140) (140;160) (160;180) (180;200) (200;220) (220;240)

Frequency of occurence (%)

Inaccuracies in demand forecasts (%)

Inaccuracies in demand forecasts (road projects)

Salling et al. (2012)

Flyvbjerg et al. (2003) Nicolaisen et al. (2012)

(15)

The UNITE Project Database (UPD)

• The convention used is as follows:

( ( ) )

forecasted forecasted actual

X X

U X − ×100

=

Under estimation of costs

(16)

• Construction costs bias derived similarly:

– U is percent inaccuracy,

– Xa is the actual traffic after the project is opened – Xf is the forecasted traffic on the decision to build

• Combination of two database samples

0 10 20 30 40 50

(-100;-80) (-80;-60) (-60;-40) (-40;-20) (-20;0) (0;20) (20;40) (40;60) (60;80) (80;100) (100;120) (120;140) (140;160) (160;180) (180;200) (200;220) (220;240)

Frequency of occurence (%)

Inaccuracies in construction costs (%)

Inaccuracies in construction cost (road projects)

Salling et al (2012) Flyvbjerg et al. (2003)

Nicolaisen et al. (2012)

(17)

Results (RCF): Monte Carlo simulation

(18)

Conclusions

• Feasibility risk assessment can be carried out by using historical experience stemming from RCF in order to obtain interval

results

• An important aspect in RCF and UNITE is to set and validate input parameters. Hence, empirical data enter the

assessment.

• The RCF approach has been illustrated on a case example concerning the construction of a new fixed link, the HH-

Connection, between Denmark and Sweden.

• Clearly vital to include uncertainties within socio-economic analyses in order to validate results

(19)

Perspectives

• Recovering of further data (UPD) with regard to both the

demand forecast uncertainty as well as the construction costs through large-scale research study

• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model combined with overconfidence theory allows for expert opinions (SIMSIGHT)

• More info on UNITE can be found: (www.transport.dtu.dk/unite)

• An international conference on the topic is scheduled in

September 2013 – a specific call will be posted in the upcoming month.

(20)

SIMSIGHT: Decision Conferencing (DC)

• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model

• Enables to include Stakeholders and Decision-makers in an early stage, i.e. to include experts opinion on MIN and

MAX values as entries to the Monte Carlo simulation

(21)

Results from DC and RSF

(22)

SIMSIGHT: Overconfidence

(23)

Perspectives

• Recovering of further data (UPD) with regard to both the

demand forecast uncertainty as well as the construction costs through large-scale research study

• Producing so-called decision conferences in order to achieve better input parameters to the UNITE-DSS Model combined with overconfidence theory allows for expert opinions (SIMSIGHT)

• More info on UNITE can be found: (www.transport.dtu.dk/unite)

• An international conference on the topic is scheduled in

September 2013 – a specific call will be posted in the upcoming month.

(24)

Thank you for your attention!

Affiliation:

Associate Professor, PhD Kim Bang Salling Department of Transport Technical University of Denmark kbs@transport.dtu.dk

Referencer

RELATEREDE DOKUMENTER

Objectives: To study the association between adoption and use of EHRs in primary care clinics and HCH certification, including use of clinical decision support tools,

Building on this model, we investigated how decision makers communicate and share their intuitive judgments in a data-driven decision making process where the BI systems are

In order to capture the broad scope of entrepreneurship education in an inclusive, yet specific way, we have developed a categorization model which allows us to measure how

The European Council decision in July 2020 to stimulate economic recovery from the COVID-19 pandemic with the 750-billion-euro Next Generation EU (NGEU) package could mark a

The primary decision variables in the model are the machinery sizes together with the number o f tractors and their sizes. is introduced to simplify the model formulation.

“anybody in public service or duty” had committed faults or negligence in relation to the decision-making process and the administration connected with the

deeper crop insights and prescription maps to support farmers in their everyday decision-making.. 5 years of

Afterwards we derive the stochastic collocation and Galerkin methods, allowing us to combine the spectral methods with the generalized polynomial chaos meth- ods in order to