New EIA process for Vesterhav Syd initiated

The Energy Board of Appeal has cancelled and withdrawn the part of the construction licence for the Vesterhav Syd Offshore Wind Farm concerning assessment of environmental impacts, with a view to renewed processing by the Danish Energy Agency. A new EIA process has been initiated.

In its decision dated 20 December 2018, the Energy Board of Appeal completed processing a number of appeals concerning the Vesterhav Syd Offshore Wind Farm.

(2)

The Energy Board of Appeal has cancelled the part of the Danish Energy Agency’s licence to construct the Vesterhav Syd Offshore Wind Farm that concerns environmental impact assessment (EIA). An EIA supplement will now be drawn up for the specific project, and after this the Danish Energy Agency will be able to make its final decision on the matter, after consulting the public interests involved and with the right of appeal.

Energy Board of Appeal’s decision (in Danish).

Therefore, the Danish Energy Agency has today notified Vattenfall Vindkraft Vesterhav Syd P/S about initiation of a new EIA process for the Vesterhav Syd Offshore Wind Farm that will include the specific project and consultation process for the public interests involved. There will also be a right to appeal.

Construction licence for Vesterhav Nord likely to be reopened

The decision by the Energy Board of Appeal does not directly concern the Vesterhav Nord Offshore Wind Farm. However, the Danish Energy Agency also expects to reopen part of the construction licence for the Vesterhav Nord project to make a final decision with a right of appeal. The similarities between the two wind turbine projects, Vesterhav Nord and Vesterhav Syd, mean that there could also be a new EIA including public consultation for the Vesterhav Nord project. This will depend on a specific assessment.

Contact: Ture Falbe-Hansen, Head of Media Relations, cell: +45 25 13 78 46, e-mail: tfh@ens.dk

Contacts

Ture Falbe-Hansen

Head of Press (+45) 2513 7846 tfh@ens.dk Laura Andersen

Press officer (+45) 3395 0906 lrsn@ens.dk

Referencer

RELATEREDE DOKUMENTER

Delimitation of the 15 dB exclusion line for regular dwellings (blue) and cottage zones (red) at 8 m/s (calculated for low frequency noise) with already operating

The Danish Energy Authority is today soliciting new tenders for the Rødsand II Offshore Wind Farm south of Lolland.. Domestic

• In December 2018 the Danish Energy Board of Appeal published a decision concerning a specific Danish offshore wind farm. • This decision causes a need to adjust the EIA

The publication of the contract notice and the tender material kick-starts the tender process for Thor Offshore Wind Farm.. The process initially includes a pre-qualification

Undersøgelsesområdet for vurdering af påvirkningen af de landskabelige forhold er derfor afgrænset som det område, hvor havmøller og anlæg på land potentielt kan have en visuel

For at vise samspillet mellem Thor Havmøllepark og vind- mølleparkerne Vesterhav Syd og Vesterhav Nord er der des- uden valgt to fotopunkter, fotopunkt 4 og 5, fra kysten ud for de

Sedimentspildet i demonteringsfasen er vurderet til at være det samme eller mindre end i anlægsfasen (se afsnit 5.1– vandkvalitet hydrografi), og påvirkningsgraden

Flere høringssvar peger på negative påvirkninger af fugle i området og ønsker projektets påvirkning af fuglelivet be- lyst i miljøkonsekvensrapporten herunder særligt redegø-