Time reference UTC / GPS? Time reference options given in TF 3.2.5, section 5.1 shall be selected as the Universal Time, Coordinated (UTC)

N/A
N/A
Info
Hent
Protected

Academic year: 2022

Del "Time reference UTC / GPS? Time reference options given in TF 3.2.5, section 5.1 shall be selected as the Universal Time, Coordinated (UTC)"

Copied!
2
0
0

Indlæser.... (se fuldtekst nu)

Hele teksten

(1)

HR3 meeting at ENS -11.02.2014 – on grid code compliance

Question Response

Which grid code version will be applied for the HR3 project?

The tender material will refer to the Danish grid code TF 3.2.5:2010. An updated grid code will be released later this year. However, the operator is not obligated to implement the updated grid code, but has the choice between the updated and the existing from 2010.

Where is the POC, PCC and Voltage reference point?

The POC is at 33 kV on the horn of the low voltage side of the transformer on the platform

The PCC is at the 220 kV bus bar at the land based substation The Voltage reference point is at the PCC

More information of the GIS system at the transformer platform was requested?

Meeting on platform details?

When the final design specifications of the platform components are released relevant parts will be published.

ENS will take action.

Requirements to the electrical simulation model?

As specified in TF 3.2.5:2010, Annex 2

Harmonics – how to calculate these? ENDK provides impedance plot for the frequency range.

Short Circuit impedance – max, min, typical for the area?

The general short circuit specification given in TF 3.2.5 section 4 can be applied in general design considerations. When the detailed design phase is completed and the specific data for the infrastructure is available a specific impedance plot will be exchanged with the selected developer.

Time reference UTC / GPS? Time reference options given in TF 3.2.5, section 5.1 shall be selected as the Universal Time, Coordinated (UTC).

Rated power – where to be measured? The rated power shall be measured at the Wind Power Plant terminals – the POC.

Rapid voltage changes – during switching? The specifications for Rapid Voltage Changes shall be understood as defined in IEC 61000-3-7, clause 3 and 10.

Available power calculation?

Prediction of not delivered production?

Compliance test – accuracy of estimated not provided power?

The algorithm, methodology and accuracy for estimation of available production shall be approved as a part of the grid connection compliance process and follow the specifications given in Energinet.dk market regulation E and related

annexes. Compliance shall be verified as specified in TF 3.2.5.

annex 5.

Protection settings As per specifications in TF 3.2.5 section 6 and related annex.

Fault recorder? Fault record systems shall be installed and configured as specified in TF 3.2.5 section 7.4

Vector jump relays – ROCOF? ROCOF and Vector jump relays must not be installed as they could cause server control situations in case of failures.

High wind ride through requirements? A high wind ride through functionality shall be provided.

According to TF 3.2.5., section 5.7.3 a stepwise reduction in active power in case of high wind, the steps shall be less than 25% of the rated power. The typical time period shall be larger than 3-5 minutes. Typical wind speed range for down

regulation is 6 m/s. Wind speed average period shall be 10 minutes.

Voltage levels – max. 36kV at POC? According to the specifications given in TF 3.2.5 section 3 the maximum voltage variation for the normal operational range

(2)

shall be +/-10%. The specific operational voltage and

tolerance within the normal operational voltage range at the POC shall be negotiated between the parties after the detailed design is completed.

Reactive compensation at zero production The Wind Power Plant shall be compensated in order to be neutral at the POC at zero production according to TF 3.2.5 section 5.9.4.

Loading of cable in case of failure + / - ?? The +/- specification for the max. loading of the transmission cable seems not to be relevant. Only the positive deviation is relevant.

Number of wind turbine in maintenance shall be provided?

Number of wind turbines in operation as well as number of wind turbines in maintenance shall be informed according to TF 3.2.5, Annex 4.

Referencer

RELATEREDE DOKUMENTER

The numerical experiments presented in Section 3 indicate that to preserve the accuracy of the velocity and vorticity approximation over a fixed time interval.. [0,

3) Maximum precool time ∆: The maximum precool time is individual for each display case and could either be based on experiments or experience. It should approximately be the time

a) According to RfG, Natural Gas shall be expressed in kWh in the Transmission System and the Distribution Network. Billing in the Distribution Network shall be made in accordance

According to section 5(2) of the Executive Order, persons other than those referred to in subsection (1) could gain access to the defence areas in Greenland established pursuant

- Der udarbejdes en mail med en lille præsentation af medlemmerne, hvor der ligeledes opfordres til at de sender en beskrivelse retur på mail eller til bestyrelsen. - Det

Figure 2 is used for further analysis and in figure 5 is shown the relationship between the vegetative period (time from propaga- tion to shortday) and the generative period (time

3. The total reserve capacity for FCR-D upwards required for the Nordic synchronous area shall be dimensioned to be at least equal to the imbalance caused by the reference incident

If the six-month time-limit set out in section 5 has expired, paternity proceedings, other than in the case of erroneous recording (section 23), can only be reopened if