Market Dialogue on

Thor Offshore Wind Farm

Director General Kristoffer Böttzauw Danish Energy Agency,

Copenhagen, 25 Nov 2019

(2)

Danish Energy Agency

ENERGY EFFICIENCY

RENEWABLE ENERGY

Renewable Energy Administration

ENERGY SUPPLY &

REGULATION OF WATER AND WASTE Subsoil

Resources and Risk CLIMATE AND

ENERGY ECONOMICS TELECOMS

GLOBAL COOPERATION

The Danish Energy Agency (DEA)

An agency under the Ministry of Climate, Energy and Utilities – establised 1976

Offshore wind Onshore wind Solar

Bioenergy

(3)

The Danish Energy Agreement of 2018

A 10 year plan (2020-2030)

- Based on broad political support (9 out of 10 parties) Policy targets

• 55 % renewable energy in 2030

• Net zero CO2 emissions by 2050

• Min. 2,400 MW offshore wind by 2030 (Thor 1

st

OWF) Principles of the Agreement

• The Market shall as far as possible facilitate the green transition

• The ambition is, within a few years, to be able to generate green electricity without state subsidies,

• Electricity will be the dominant source of energy

(4)

Additional policy framework, new govt. 2019

A target of reducing national greenhouse gas emissions in 2030 by 70%

Focus:

• Energy

• Transport

• Agriculture

Energy island for 10 GW offshore wind

(5)

Danish offshore wind track record

Timeline for offshore wind farms in Denmark (> 100 MW)

2002: Horns Rev 1 – 160 MW

2003: Nysted (Rødsand) 165 MW 2009: Horn Rev 2 – 209 MW

2010: Rødsand 2 – 207 MW 2012: Anholt - 400 MW

2019: Horns Rev 3 – 400 MW

2021: Kriegers Flak – 600 MW, interconnector DK/DE 2023: Vesterhav Nord & Syd – 350 MW, nearshore 2027: Thor Offshore Wind Farm – 800 – 1,000 MW 2030: 2 x min. 800 MW in the pipeline…

(6)

• 43 % wind power in the electrical system

• 99,996 % security of supply

A flexible and integrated energy system

(7)

The Danish Tender Model for Offshore Wind

Broad long-term political commitment One Stop Shop

TSO does preliminary studies

Price is the primary award criteria Support will be granted as a CfD for a

period of 20 years

Guaranteed access to the grid Efficient and transparent electricity

market Dialogue and negotiation with

prequalified bidders

(8)

Thank You For Your

Attention!

Referencer

RELATEREDE DOKUMENTER

The parties to the Energy Agreement of 2018 also decided as something new for Danish offshore wind tenders, that the offshore substation and the grid connection from the wind farm

Thor connection, new model -> Energinet provide POC and settlement in a new 220 kV substation 2-5 km inland from shore (POC-2), by constructing, operating and own the part of

The Danish Energy Agency has prequalified a total of six consortia and companies to participate in the tender for Denmark's largest offshore wind farm to date: Thor Offshore Wind

The Danish Energy Agency publishes detailed material concerning central elements and questions, which will be discussed with market players at the market dialogue on 25 Nov 2019

To follow up on the market dialogue on Thor Offshore Wind Farm held in November 2019, the Danish Energy Agency now publishes answers to questions raised as part of the dialogue on

The Danish Energy Agency publishes detailed material concerning central elements and questions, which will be discussed with market players at the market dialogue on 25 Nov 2019

To follow up on the market dialogue on Thor Offshore Wind Farm held in November 2019, the Danish Energy Agency now publishes answers to questions raised as part of the dialogue on

Today, the Danish Energy Agency (DEA) publishes the material for the market dialogue for the upcoming Hesselø Offshore Wind Farm (OWF) tender.. The DEA here invites potential