• Ingen resultater fundet

3.   Project background

3.3   Future expansions

It is therefore important to emphasize that during the decision‐making stages of grid expansion, Energinet  has to take into account not only the specific requirements of the project at hand (as in the current Western  and Southern Jutland projects), but also the wider system requirements for setting up a robust, economic,  operable and environmentally friendly system. 

 

Based on the evaluation of the individual transmission alternatives, the 400 kV solution is still considered the  most efficient alternative due to its built‐in robustness and the possibility of integration with the existing  transmission grid without the need to introduce additional advanced systems for control and regulation of  power flows in the overall transmission grid. 

 

As 400 kV OHL and UGC solutions fulfill the planning criteria outlined in Section 2.3 and in view of the  limitations of 150 kV and 220 kV transmission alternatives, only 400 kV HVAC and HVDC transmission  alternatives are investigated in depth in this report. 

 

In Section 3.3, future grid expansion is discussed. The purpose of the section is to outline the need for future  expansions of the transmission grid in Denmark. 

 

3.3 Future expansions 

The impact of the new planning assumptions has been tested on the possible future grid structure presented  in RUS plan 2017. The operational scenarios chosen for the studies provide operational considerations for  several scenarios, including high and low levels of renewable generation combined with various levels of  demand and different patterns of cross‐border energy exchanges. 

 

The performance of the transmission grid has been evaluated against Energinet's planning standards and the  predefined operational scenarios. 

 

Power flow calculations have been conducted for the following years: 

 

‐ 2024 (including Viking Link and the Endrup‐Klixbüll and Endrup‐Idomlund 400 kV transmission lines,  no new offshore wind power plants); 

‐ 2028 (including the first new offshore wind power plant at Ringkøbing Fjord connected in  Idomlund); 

‐ 2031 (including the second new offshore wind power plant at Horns Rev connected in Stovstrup); 

and 

‐ 2040 (including all new offshore wind power plants in accordance with Section 2.6.2.3)   

Besides the already identified 400 kV grid expansion requirements in the Western and Southern part of  Jutland, the following additional 400 kV transmission lines are (according to RUS plan 2017) required in order  to accommodate future capacity needs derived from the revised planning assumptions: 

   

1. 400 kV Idomlund‐Tjele (circuit 2) required to support increase of wind and solar power in the  Western part of Jutland; 

2. 400 kV Endrup‐Idomlund (circuit 2), required to support increase of wind and solar power in the  Western part of Jutland; 

3. 400 kV Ferslev‐Tjele, required to support an increase in wind and solar power in the northern part  of Jutland; 

4. 400 kV Ferslev‐Vester Hassing, required to support an increase in wind and solar power in the  northern part of Jutland; 

5. 400 kV Landerupgård‐Revsing, required to facilitate the market and ensure supply to the Eastern  part of Jutland and Funen; 

6. 400 kV Hovegård‐Ishøj, required to support the new wind power plants at Kriegers Flak; 

7. 400 kV Hovegård‐Bellahøj, required to ensure security of supply in the Copenhagen region; and  8. 400 Hovegård‐Bjæverskov, required as a general reinforcement of the 400 kV transmission grid. 

 

In Figure 8, required 400 kV grid expansions are highlighted, where green (ID2) indicates the considered  Idomlund‐Endrup transmission line and amber coloured lines indicate additional grid expansion 

requirements. 

 

 

Figure 8 Required expansions of the 400 kV transmission grid (numbers indicate project IDs from the bulleted  list on the previous page). 

On the list of required 400 kV grid expansions is the installation of a second 400 kV circuit on the existing 400  kV overhead line between the existing substations at Idomlund and Tjele (ID 1). This additional 400 kV circuit  effectively links the Western part of the transmission grid with the existing 400 kV backbone of Jutland, thus  establishing a redundant (N‐1 secure) supply for the 400 kV substation at Idomlund, a prerequisite for grid  connection of the assumed Ringkøbing 1 offshore wind power plant (800 MW). The proposed plan is to  establish this additional 400 kV circuit by refitting the existing 400 kV Donau towers of the OHL between  Idomlund and Tjele, using the same right of way as shown in Figure 9. 

 

  Figure 9 Proposed refitting of existing 400 kV Donau towers. 

 

The analysis also shows that additional transmission capacity is required in the Western part of Jutland due  to future grid connections of offshore wind power plants at Ringkøbing and Horns Rev. The required  transmission capacity will be established by installing a second 400 kV circuit between the substations at  Endrup and Idomlund (ID 2). This expansion should be completed by 2030. 

 

The connection of large‐scale offshore wind power plants will result in significant power infeed at the  connection points and in the adjacent transmission grid. A firm and long‐term strategic development plan for  future offshore wind power plants in Denmark will ensure the corresponding development of the 

transmission grid, facilitating timely coordination and commissioning of necessary grid expansions in relation  to the completion of the respective offshore wind plants. 

 

Offshore wind power facilities with capacities of 600‐800 MW will require the locations of these facilities to  be determined according to a long‐term development plan in order to ensure that the transmission grid is  developed accordingly with respect to timeliness, robustness and cost‐effectiveness. Without such a plan,  considerable costs could result from the suboptimal choice of non‐robust solutions today. 

 

The specific transmission capacity requirements as well as the optimal time for the commissioning of these  400 kV transmission lines will be analysed in more detail as part of the upcoming RUS plan 2018.